March 6, 2013
Chile’s supreme court has imposed a fine of USD1.8 million on Chile's main power transmission company Transelec SA for delaying the construction of the El Rodeo–Chena power line in Maipo province.
March 6, 2013
Bolivia’s government is ready to provide compensation to Spanish electricity grid operator Red Electrica de Espana (REE) for the expropriation of its local unit Transportadora de Electricidad (TDE).
March 6, 2013
The national power company of Mexico, Comisión Federal de Electricida (CFE) has awarded a USD54 million contract to Spain-based Abengoa S.A. As per the contract, Abengoa will be responsible for the construction of two substations and a 201 km long, 400 kV transmission line in the northwest state of Sonora.
March 5, 2013
Brazil’s Ministério Público Federal (MPF) or the Federal Public Ministry has announced a public inquiry on the environment impacts of the BRL3 billion Tucurui–Macapa–Manaus transmission line linking the remote Amazonian communities to the national power grid.
March 1, 2013
Brazilian power company Furnas Central Electric SA (Furnas), a subsidiary of Eletrobras, has invested BRL2.39 billion or 91 per cent of its budget estimates in 2012.
March 1, 2013
Brazil's state-owned power utility Companhia Paranaense de Energia (Copel) has announced an investment of BRL46 million to upgrade its power network in Curitiba, the capital of the southern state of Parana.
February 28, 2013
Argentina's federal power utility Consejo Federal de Energía Eléctrica (CFEE) has launched an international tender for the design and supply of material and equipment, and installation and commissioning of the 121 km, 132 kV Lujan–P. Industrial transmission line.
February 28, 2013
Brazilian power company Furnas Central Electric SA (Furnas), a subsidiary of Eletrobras, has invited competitive bids for supplying and commissioning protection and controls systems for a 345/230 kV autotransformer bank at the Bandeirantes substation.
February 27, 2013
Brazil power regulator Agencia Nacional de Energia Eletrica (Aneel) has announced a new rule for wind-energy companies as per which the developers participating in auctions for contracts to sell electricity from wind farms will also be responsible for connecting their power plants to the grid.
February 26, 2013
Brazilian power utility Centrais Elétricas do Norte do Brasil S.A (Eletronorte), a subsidiary of state-owned Centrais Eletricas Brasileiras (Eletrobras), has invited bids for expanding its 230/69/13.8 kV Altamira power substation located in the northern state of Para.
February 26, 2013
Brazilian power generation company Companhia Paulista de Força e Luz (CPFL) Geracao, a subsidiary of CPFL Energia, has signed an agreement for the concession of the Piracicaba power substation located in the southern state of Sao Paulo.
February 22, 2013
Venezuelan national power company Corporación Electrica Nacional, S.A (Corpoelec) has planned to initiate installations of 10 new substations with cumulative capacity of 750 MVA in 2013. The substations are likely to be ready by 2014.
February 22, 2013
The Catamarca province’s regulators in Argentina have decided to award the contract of construction of a 132 kV substation, which is a part of a new connection between Catamarca city and the national power network, without auction.
February 22, 2013
ProInversión, Peru's private investment promotion agency, has awarded a 30-year concession contract for building and operating the 220 kV Machu Picchu–Quencoro–Onocora–Tintaya transmission line project to Abengoa Peru, which is a subsidiary of the Spain-based Abengoa S.A.
February 21, 2013
Brazil federal government-owned power company Centrais Eletricas Brasileiras (Eletrobras) is planning to boost revenues by 30 per cent by selling its assets over the next three years.
February 21, 2013
The governments of Brazil and Guyana are looking to strengthen bilateral relations, especially in the areas of construction of hydroelectric power plants.
February 19, 2013
Brazilian power company Furnas Central Electric SA (Furnas), a subsidiary of Centrais Eletricas Brasileiras (Eletrobras), is seeking contractors for the construction of the new Jacarepagua substation in Rio de Janeiro state.
February 19, 2013
Chile’s federal copper producer Codelco has submitted an environment clearance application to construct a 760 MW combined cycle plant in the Antofagasta region.