Project Update

Parinas–Likanantai Transmission Line Project, Chile [free access]

November 5, 2019

Developer: Yet to be selected

 

Project details and status: The project entails the construction of a 500 kV double-circuit line to be initially energised at the 220 kV level, and construction of the Likanantai substation with a capacity of about 1,000 MVA.

 

In September 2019, the Chilean coordinator of the national electricity system, Coordinador Eléctrico Nacional (CEN), issued bidding terms and conditions for the tender containing the 500 kV Parinas–Likanantai Transmission Line Project. Under this tender, which was announced in April 2019, CEN offered eight new projects with total referential investment of USD232 million, and published its bid terms after holding consultations with the players. These projects form part of the country’s 2017 transmission plan, and are also included in the Decree No. 4/2019, published on January 9, 2019.

 

The proposals for the project will be received by CEN till November 20, 2019. Administrative and technical offers will be opened on November 21, 2019 and economic bids on February 6, 2020, with a scheduled award date of February 14, 2020.

 

The project is scheduled for commissioning in 2025.