Vietnam’s EVN NPT invites bids for 500 kV transmission project [free access]

December 1, 2017

Vietnam’s National Power Transmission Corporation (EVN NPT) has invited two bids for the supply of cables and conductors for the 500 kV West Hanoi–Thuong Tin transmission line under the World Bank-funded Transmission Efficiency Project (TEP).

 

The first contract involves the supply and delivery of optical cables and accessories, insulators and fittings while the second contract involves the supply and delivery of conductors and earth wires.

The last date for submission of the first bid is January 4, 2018, followed by the second bid’s deadline by January 9, 2017.

 

The contract duration for both the bids is 180 days from the award of contract.